江东国际一期工程地下室施工临时照明方案低压_施工临时照明方案
江东国际一期工程地下室施工临时照明方案低压由刀豆文库小编整理,希望给你工作、学习、生活带来方便,猜你可能喜欢“施工临时照明方案”。
江东国际一期工程项目部
江东国际一期工程
地 下 室 施 工 临 时 照 明 方 案
编制人:
审核人:
批准人:
日期:
江东国际一期工程项目部
目 录
一、工程概述„„„„„„„„„„„„„„„„„„„„„„3
二、编制依据„„„„„„„„„„„„„„„„„„„„„„4
三、现场勘察及初步设计„„„„„„„„„„„„„„„„„41、现场情况„„„„„„„„„„„„„„„„„„„„„42、地下室两层照明用电设计„„„„„„„„„„„„„„43、电源简介„„„„„„„„„„„„„„„„„„„„„54、总用电量的设计计算„„„„„„„„„„„„„„„„5
四、线路布置及导线截面积选择„„„„„„„„„„„„„„6
五、地下室照明线路的敷设„„„„„„„„„„„„„„„„9
六、电线电缆选择„„„„„„„„„„„„„„„„„„„„9
七、地下室施工临时照明图„„„„„„„„„„„„„„„„9
八、临电配电箱安装„„„„„„„„„„„„„„„„„„„9
九、管理措施„„„„„„„„„„„„„„„„„„„„„„9
十、安全措施„„„„„„„„„„„„„„„„„„„„„„10
十一、预防事故的措施„„„„„„„„„„„„„„„„„„10
十二、临电节能„„„„„„„„„„„„„„„„„„„„„11江东国际一期工程项目部
一、工程概述
工程名称:江东国际一期工程
建设单位:成都蜀鑫房地产开发有限公司 施工单位:成都市蒲江七建工程有限责任公司 设计单位:中国建筑技术集团有限公司 监理单位:四川陵州建设监理有限责任公司 建设地点
蒲江县鹤山镇朝阳大道 建筑概况:
本项目本工程为成都蜀鑫房地产开发有限公司江东国际一期,总建筑面积约137872.5m2。
地上共有5栋建筑,其中5#楼1、2单元地上16层,一层带商业网点;6#楼1、2单元地上16层,3单元地上17层,一、二层带商业网点;7号楼1、2单元地上18层,一层有商业网点;8#,9#楼地上均为26层。
地下室建筑面积22096.34m2,划分7个防火分区。结构为现浇钢筋混凝土-剪力墙结构。地下一层建筑面积18581.16m2,一至五防火分区为汽车库,停车总数527辆,,六、七防火分区为自行车库,局部地下二层目前为无使用功能的封闭空间。江东国际一期工程项目部
二、编制依据
《建筑工程施工现场供电安全规范》GB50194-93中国建筑工业出版社 《施工现场临时用电安全技术规范》JGJ46-2005中国建筑工业出版社 《低压配电设计规范》GB50054-2011中国计划出版社
三、现场勘察及初步设计
1、现场情况
本工程两层地下室完全处于地下,四面为钢筋混凝土剪力墙。如果要进行后续各分部分项工程施工,照明问题需要解决。根据施工进度安排,主体完成后,设备安装(包括空调、消防、暖通、配电)、水电安装和土建装修都将进入地下室。因此统筹考虑地下室的照明,无论从施工、还是安全角度来说都是非常必要的。
2、地下室两层照明用电设计
2.1、根据GJG46-2005规范的要求,地下室长期处于潮湿环境中,其照明线路采用36V安全电压供电。
2.2、本着既满足施工和安全要求,又节约用电的原则,设置照明线路和灯具,参考室内照明用电定额资料,取照明容量为1.5W/㎡。选定灯具为60W白炽灯,其中在特别场所(如水箱间、泵房等潮湿的地方)用防水防尘罩。需要明配管的地方使用PVC阻燃线管盒明配;根据设计出的图纸进行负荷计算,并据此选取断路器、漏电保护器、隔离开关等。对于结构完成的区域安装临电照明。
2.3、地下室一层照明按防火分区基本划分为7个区域,二层照明一个区域,江东国际一期工程项目部
每个区域集中设置开关箱,每个开关箱分支路,当一个支路较长且有车库、走道等不同性质的地方的时候应设置开关分开通断电。因二次墙的原因导致原回路不能连通,可使用明敷设pvc阻燃线管进行连通。施工过程中局部照明强度不足的部分,采取移动箱供电照明的措施。线路的设计布置及灯位的安装,见后附地下室一、二层平面布置图。
2.4、所有开关箱出线支路的照明线路均采用相线(红、绿、黄色)、零线(蓝色)、PE线(黄绿双色线)。
3、电源简介
利用现在施工场地220/380V总临电配电箱做电源给地下室临时照明供电。再利用分配电箱配电、局域开关箱控制。因地下部分施工采用低压照明,考虑到线路损耗,所以在地下室室内地面设置行灯变压器,由室外总配引进220/380v电源,变压器可将220/380v转换为36v安全电压供照明。输入级装设30mA/2P小型漏电保护器,变压器外壳和低压36v一侧应接地保护。36v输出端设短路保护断路器或熔断器。36v照明线路可用瓷瓶架线敷设,或采用穿难燃线管敷设。灯具应采用防水灯头,或带护网的的防水灯具,配用36V灯泡。以上设备按照明功率大小选择变压器和导线,具体附后。
4、总用电量的设计计算: ㈠地下一层用电总负荷: P=18581.16×1.5W/㎡=27871W=27.87kW 灯具数量:27.87kW÷60W/盏=465盏 按36V安全电压考虑: 总电流为:27871÷36=774A 用电总容量: 江东国际一期工程项目部
P总=K·P=1.1×27.87 =30.66 kVA ㈡地下二层用电总负荷: P=3515.18×1.5W/㎡=5273W=5.27kW 灯具数量:55.27 kW÷60W/盏=88盏 按36V安全电压考虑: 总电流为:5272÷36=146.5A 用电总容量: P总=K·P=1.1×5.27 =5.79kVA
四、线路布置及导线截面积选择
根据各条线路的电流强度和现场的实际情况,地下室一层7个照明区域的照明线路按8条回路布置,地下室二层按2条回路布置,即每台变压器为一个单独回路。每一输电线路按不同线径分段接入。供电线路选择BV型铜芯导线。横截面积分别为:2.5 mm2、4 mm2、6mm2、10 mm2、16 mm2、25mm2。4.1、AL1开关箱导线截面积验算
W1支路安装灯泡26盏,I=26盏×60W/36=43.3A(6mm2导线满足要求)W2支路安装灯泡23盏,I=23盏×60W/36=38.3A(6mm2导线满足要求)W3支路安装灯泡23盏,I=22盏×60W/36=36.7A(6mm2导线满足要求)回路总电流=43.3+38.3+36.7=118.3A(25 mm2导线满足要求)总功率=4260W,选取5000VA行灯变压器1台。4.2、AL2开关箱导线截面积验算
W1支路安装灯泡24盏,I=24盏×60W/36=40A(6mm2导线满足要求)江东国际一期工程项目部
W5支路安装灯泡16盏,I=16盏×60W/36=26.7A(4mm2导线满足要求)回路总电流=40+26.7=66.7A(10 mm2导线满足要求)总功率=2400W,选取3000VA行灯变压器1台。
W2支路安装灯泡20盏,I=20盏×60W/36=33A(6mm2导线满足要求)W3支路安装灯泡21盏,I=23盏×60W/36=35A(6mm2导线满足要求)W4支路安装灯泡22盏,I=22盏×60W/36=36.7A(6mm2导线满足要求)回路总电流=33+35+36.7=104.7A(25mm2导线满足要求)总功率=3780W,选取5000VA行灯变压器1台。4.3、AL3开关箱导线截面积验算
W1支路安装灯泡22盏,I=22盏×60W/36=36.7A(6mm2导线满足要求)W2支路安装灯泡14盏,I=14盏×60W/36=23.3A(4mm2导线满足要求)W3支路安装灯泡20盏,I=20盏×60W/36=33A(6mm2导线满足要求)W4支路安装灯泡18盏,I=18盏×60W/36=30A(6mm2导线满足要求)回路总电流=36.7+23.3+33+30=123A(25 mm2导线满足要求)总功率=3780W,选取5000VA行灯变压器1台。4.4、AL4开关箱导线截面积验算
W1支路安装灯泡23盏,I=23盏×60W/36=38.3A(6mm2导线满足要求)W2支路安装灯泡25盏,I=25盏×60W/36=41.7A(6mm2导线满足要求)W3支路安装灯泡25盏,I=25盏×60W/36=41.7A(6mm2导线满足要求)回路总电流=38.3+41.7+41.7=121.6A(25 mm2导线满足要求)总功率=4380W,选取5000VA行灯变压器1台。4.5、AL5开关箱导线截面积验算江东国际一期工程项目部
W1支路安装灯泡23盏,I=23盏×60W/36=38.3A(6mm2导线满足要求)W2支路安装灯泡22盏,I=22盏×60W/36=36.7A(6mm2导线满足要求)W3支路安装灯泡21盏,I=23盏×60W/36=35A(6mm2导线满足要求)回路总电流=38.3+36.7+35=110(25 mm2导线满足要求)总功率=3960W,选取5000VA行灯变压器1台。4.6、AL6开关箱导线截面积验算
W1支路安装灯泡23盏,I=23盏×60W/36=38.3A(6mm2导线满足要求)W2支路安装灯泡21盏,I=23盏×60W/36=35A(6mm2导线满足要求)W3支路安装灯泡24盏,I=24盏×60W/36=40A(6mm2导线满足要求)回路总电流=38.3+35+40=113.3(25 mm2导线满足要求)总功率=4080W,选取5000VA行灯变压器1台。4.7、AL7开关箱导线截面积验算
W1支路安装灯泡10盏,I=10盏×60W/36=16.7A(2.5mm2导线满足要求)总功率=600W,选取1000VA行灯变压器1台。4.3、B2AL开关箱导线截面积验算
W1支路安装灯泡24盏,I=24盏×60W/36=40A(6mm2导线满足要求)W2支路安装灯泡19盏,I=19盏×60W/36=31.7A(4mm2导线满足要求)回路总电流=40+31.7=71.7(16 mm2导线满足要求)总功率=2580W,选取3000VA行灯变压器1台。
W3支路安装灯泡22盏,I=22盏×60W/36=36.7A(6mm2导线满足要求)W4支路安装灯泡23盏,I=23盏×60W/36=38.3A(6mm2导线满足要求)回路总电流=36.7+38.3=75A(17mm2导线满足要求)江东国际一期工程项目部
总功率=2700W,选取3000VA行灯变压器1台。
五、地下室照明线路的敷设
按照地下室施工照明平面图的要求,分回路敷设导线,低压变压器一次侧(220V或380V)采用10mm2绝缘橡套铜芯电缆;二次侧(36V安全电压侧)采用BV型铜芯导线,横截面积分别为:2.5 mm2、4 mm2、6mm2、10 mm2、16 mm2、25mm2。
导线的固定,横担:采用40×4角钢,用膨胀螺栓固定在框架柱上,每根角钢上安装两个绝缘瓷瓶,每隔一根柱安装一组横担。安装高度大于2.6m。或采用阻燃PVC线管敷设。
六、电线电缆选择
所有要使用的电线、电缆、电气元件、灯具应符合国家安全规范使用的标准及(CCC)认证。
七、地下室施工临时照明图
见地下室一、二层施工照明平面布置图
八、临电配电箱安装
所有的临电配电箱均为下进下出,照明开关箱采用用挂墙用膨胀螺栓固定的安装方式,安装应牢固可靠,挂装的位置空间应宽大、整洁、干燥有足够的空间进行安装、维修工作并不得放置在易燃、易爆的场所。
箱体里配线整齐、压接线符合要求。
九、管理措施
1)项目部建立完善的安全用电制度,确立专职安全维护电工。各临电配电箱、开关箱应设置明显的标识和铭牌,标识该箱的专职电工及联系电话。2)在配电箱放置处应设置警示牌;项目部应按时向施工班组发放施工安全技江东国际一期工程项目部
术交底介绍技术内容和注意事项,并应在技术交底文字资料上履行交底人和接受人的签字手续,注明交底日期。
3)建立健全的维修、检查和拆除制度,并及时以书面的形式进行记录。4)定期对项目部管理人员、施工班组进行安全培训,提高人员的安全用电意识,杜绝乱拉、偷盗等行为,当照明用电有特别需要时,应及时向项目部领导进行汇报并许可后由专职电工进行作业。
5)当线路或者配电箱发生事故时应立即向项目部专职管理人员汇报,并许可后安排专职安全电工或其他专职人员就行维修。
十、安全措施
1)、施工现场配电箱必须逐级设置漏电保护装置,实行分级保护且各级漏电保护器的额定漏电动作电流和额定漏电动作时间应合理配合,相互匹配,使之具有分级保护的功能。
2)、所有的电线、电缆、配电箱箱体和电气元件、照明设备等在进场使用之前必须要进行外观检查、校验、试验确保无误符合规范要求后方能使用。在一些特别的场所应使用一些特别的灯具。
3)、二、三级配电箱放置地方应可靠、干燥、宽畅、通风;周围不得堆放任何妨碍维修、操作的施工机具和物品;
二、三级箱应装设在固定、稳定的支架上距地应在1.2-1.5米之间并放置端正、牢固;放置时安装完成后确保接地、绝缘良好后方可供电使用。
4)、配电箱、开关箱必须按照下列顺序操作: 送电操作顺序为:总配电箱→分配电箱→开关箱; 停电操作顺序为:开关箱→分配电箱→总配电箱。
十一、预防事故的措施江东国际一期工程项目部
1)项目部设立专职电工定期对照明线路进行检查,检查时必须配备专用的电工工具(绝缘鞋、绝缘手套等)并按照安全规程进行检修。
2)三级箱和二级箱所使用的断路器应该经过整定试验并且符合要求,其中漏电保护器漏电动作前后应该合理有序。
3)所有地下室施工临时照明所用的照明配电箱其金属外壳必须接地,接地电阻小于1欧姆。
4)所有地下室施工临时照明电线、电缆均应该符合安全要求即绝缘良好无划伤。
5)项目部应建立健全的安全用电的保护制度,并定期对施工人员进行“安全用电”的培训,施工安全技术交底应及时落实到位。
6)当临时照明电路拆除时应统一规划、指挥并注意人员的分配、拆除的方法及保护的措施等。
十二、临电节能
1)线路较多的回路或因二次结构未有开关的应增设开关。2)使用不到的区域可以断电节能。